Justia U.S. 3rd Circuit Court of Appeals Opinion Summaries

Articles Posted in Utilities Law
by
The case involves a dispute over the Federal Energy Regulatory Commission (FERC) allowing a new auction rule to apply retroactively to a pending auction. This auction was administered by PJM Interconnection L.L.C., an entity responsible for running the auction. The petitioners, electric suppliers and their trade associations, contended that FERC's orders violated the filed rate doctrine, which forbids retroactive rates.The United States Court of Appeals for the Third Circuit found that the Tariff Amendment was retroactive because it altered the legal consequence attached to a past action when it allowed PJM to use a different Locational Deliverability Area (LDA) Reliability Requirement than the one it had calculated and posted. The court noted that the Tariff Amendment, therefore, violated the filed rate doctrine.The court ruled that the doctrine's predictability is crucial because electricity markets depend on it. FERC’s disregard of the filed rate doctrine created unpredictability in the markets, potentially eroding confidence in the markets and ultimately harming consumers who buy electricity in those markets.The court granted the petitions for review and vacated the portion of FERC’s orders that allowed PJM to apply the Tariff Amendment to the 2024/25 capacity auction. View "Constellation Energy Generation LLC v. FERC" on Justia Law

by
In this case, a group of electricity suppliers and their trade associations challenged orders of the Federal Energy Regulatory Commission (FERC) that permitted PJM Interconnection L.L.C., a wholesale market operator, to apply a new auction rule retroactively to a pending auction. The petitioners argued that FERC's orders violated the filed rate doctrine, which prohibits retroactive rates. The United States Court of Appeals for the Third Circuit agreed and granted the petitions, vacating the relevant parts of the orders.The central issue revolved around the Locational Deliverability Area (LDA) Reliability Requirement, a key parameter in PJM's auction process. Prior to the auction, PJM had miscalculated the LDA Reliability Requirement, which led to a potential price increase for a specific region. To correct this, PJM sought FERC's permission to amend the tariff to allow for a downward adjustment of the LDA Reliability Requirement. FERC granted this permission, allowing the new rule to apply to the ongoing auction, which the petitioners argued was a retroactive change in violation of the filed rate doctrine.The court found that the tariff amendment was indeed retroactive as it altered the legal consequence attached to a past action, specifically, PJM's calculation and posting of the LDA Reliability Requirement. The court held that the filed rate doctrine did not yield to equities and that the tariff amendment's retroactivity created instability in the electricity market. Consequently, the court vacated the portion of FERC's orders that allowed PJM to apply the tariff amendment to the 2024/25 capacity auction. View "NRG Business Marketing LLC v. FERC" on Justia Law

by
In White Deer Township, a four-mile gap in Verizon’s wireless coverage overlays Interstate 80; Verizon customers are likely to experience “dropped calls,” “ineffective call attempts,” and “garbled audio.” The area is within Bald Eagle State Forest. A 2000 Pennsylvania moratorium prohibits the construction of cell towers on state forest land, so Verizon’s options were limited. After considering several sites and antenna configurations, Verizon decided to construct a 195-foot monopole topped with a four-foot antenna on privately owned land, comprising 1.9 acres and containing a cabin, shed, pavilion, and privy. Verizon leased 0.0597 acres, in the northeast corner of the property for the tower.The Township then permitted cell towers that complied with a minimum permissible lot size of one acre; cell towers had to be set back “from lot lines and structures a distance equal to the height of the facility, including towers and antennas, plus 10% of such height.” The Zoning Board denied Verizon’s variance applications, finding that Verizon’s alleged hardship was insufficient because it was “not a hardship connected to the capacity for the property to be used reasonably, but rather, the hardship [was connected to Verizon’s] capacity to use the property as desired.” The Third Circuit affirmed summary judgment for Verizon. The denial had “the effect of prohibiting the provision of personal wireless services,” in violation of the Telecommunications Act, 47 U.S.C. 332(c)(7)(B)(i)(II). View "Cellco Partnership v. White Deer Township Zoning Hearing Board" on Justia Law

by
The Adorers, an order of nuns whose religious beliefs require them “to protect and preserve Earth,” own property in Pennsylvania. When Transco notified them that it was designing a 42-inch diameter interstate gas pipeline to cross their property, the Adorers explained that they would not sell a right-of-way through their property. Transco sought a certificate of public convenience and necessity. The Federal Energy Regulatory Commission (FERC) published notices and hosted open meetings to discuss the pipeline. The Adorers neither provided comments nor attended meetings. When FERC contacted the Adorers directly, they remained silent. Transco altered the pipeline’s route 132 times in response to public comment. FERC issued the requested certificate, which authorized Transco to use eminent domain to take rights-of-way 15 U.S.C. 717f(c)(1)(A). Transco sought an order of condemnation to take rights-of-way in the Adorers’ property. The Adorers failed to respond to the complaint.Days after the district court granted Transco default judgment, the Adorers sought an injunction under the Religious Freedom and Restoration Act (RFRA) 42 U.S.C. 2000bb-1(c). The Third Circuit rejected the Adorers’ contention that RFRA permitted them to assert their claim in federal court rather than before FERC. After the pipeline was put into service, the Adorers sought damages under RFRA. The Third Circuit affirmed the dismissal of the suit. To permit a party to reserve a claim, the success of which would imperil a FERC decision to certify an interstate pipeline, by remaining silent during the FERC proceedings and raising the claim in separate litigation would contravene the Natural Gas Act’s exclusive review framework. View "Adorers of the Blood of Christ United States Province v. Transcontinental Gas Pipe Line Co., LLC" on Justia Law

by
Warren tenders gasoline products to Colonial (a common carrier) for shipment on Colonial’s pipeline from Texas to New Jersey, where Warren has a gasoline-blending operation. The rates and conditions for the transportation services are specified in tariffs approved by the Federal Energy Regulation Commission (FERC). The tariff recognizes that the gasoline batches Colonial transports for Warren are fungible and allows Colonial to comingle gasoline from many shippers during transport. Colonial must deliver gasoline of the same volume and grade as the gasoline that was entrusted to it, with the same characteristics that influence the gasoline’s combustion performance (octane rating and distillation value), and its environmental impact, such as volatility. The tariff does not state whether “on specification” gasoline includes any “blend margin.” In 2016, FERC determined that the regulation of in-pipeline blending was outside its jurisdiction. Colonial continued giving Warren gasoline that complies with the relevant tariff but Warren claims that Colonial’s in-line blending of the gasoline with butane diminishes Warren’s ability to blend cheaper blendstocks into the gasoline. Warren regularly blends cheaper gasoline with more expensive gasoline to increase the amount of on-specification gasoline that it can sell,Warren sued for loss of profits (Carmack Amendment 49 U.S.C. 1590), conversion, unjust enrichment, and tortious interference. The Third Circuit affirmed the summary judgment rejection of the claims. Warren’s request seeks an enlargement of its rights under the FERC-approved tariff and violates the filed-rate doctrine’s nondiscrimination principle. View "George E. Warren LLC v. Colonial Pipeline Co" on Justia Law

by
The New Jersey Board of Public Utilities (BPU) ordered Altice, a cable service provider, to prorate its bills for the month in which a cable customer cancels his service, as required by New Jersey law. In federal court, Altice argued that the Proration Requirement is preempted by the Cable Communications Policy Act of 1984.The district court granted Altice judgment on the pleadings, concluding that “Younger” abstention was not warranted and that the Proration Requirement was preempted. The Third Circuit vacated. The Younger ruling was incorrect. BPU’s civil enforcement proceeding was quasi-criminal in nature and, thus, the type of proceeding to which Younger applies. BPU commenced the action against Altice by filing a formal complaint, a Show Cause Order with attributes similar to the filing of formal charges, and did so in its sovereign capacity. The proceeding was judicial in nature and ongoing when the federal complaint was filed; the proceeding implicates important state interests; and Altice has an adequate opportunity to raise its federal claims in the state proceeding. View "Altice USA Inc v. New Jersey Board of Public Utilities" on Justia Law

by
The Natural Gas Act (NGA), 15 U.S.C. 717, allows private gas companies to exercise the federal government’s power to take property by eminent domain, if the company has a Certificate of Public Convenience and Necessity from the Federal Energy Regulatory Commission (FERC); was unable to acquire the property by contract or reach agreement about the amount to be paid; and the value of the property exceeds $3,000. PennEast, scheduled to build a pipeline through Pennsylvania and New Jersey, obtained federal approval for the project and filed suit under the NGA to condemn and gain immediate access to properties along the pipeline route, including 42 properties owned, at least in part, by New Jersey or arms of the state. New Jersey sought dismissal, citing the Eleventh Amendment. The district court ruled in favor of PennEast. The Third Circuit vacated. The Eleventh Amendment recognizes that states enjoy sovereign immunity from suits by private parties in federal court. New Jersey has not consented to PennEast’s condemnation suits and its sovereign immunity has not been abrogated by the NGA. The federal government’s power of eminent domain and its power to hale sovereign states into federal court are separate and distinct. In the NGA, Congress has delegated only the power of eminent domain. View "In re: PennEast Pipeline Co. LLC" on Justia Law

by
The Natural Gas Act (NGA), 15 U.S.C. 717f(h) gives natural gas companies that hold certificates of public convenience and necessity from the Federal Energy Regulatory Commission (FERC) the power of eminent domain but does not provide for “quick take” to permit immediate possession. Transcontinental is building a natural gas pipeline through Pennsylvania, Maryland, Virginia, North Carolina, and South Carolina and needed rights of way. Transcontinental met the requirements of section 717f(h). The administrative review leading up to the certificate of public convenience and necessity lasted almost three years and included extensive outreach and public participation and an Environmental Impact Statement. Transcontinental extended written offers of compensation exceeding $3000 to each Landowner, but these offers were not accepted. The Landowners had all participated in the FERC administrative process. Transcontinental, planning to begin construction in fall 2017, filed condemnation suits The district court granted Transcontinental summary judgment, effectively giving it immediate possession, concluding that the Landowners had received “adequate due process.” The Third Circuit affirmed, rejecting an argument that granting immediate possession violated the separation of powers because eminent domain is a legislative power and the NGA did not grant “quick take.” Transcontinental properly obtained the substantive right to the property by following the statutory requirements, which are not similar to “quick take” procedures, before seeking equitable relief to obtain possession. View "Transcontinental Gas Pipe Line Co., LLC v. Permanent Easements for 2.14 Acres" on Justia Law

by
After initiating Chapter 11 bankruptcy proceedings, Debtors entered into an Agreement: NextEra would acquire Debtors’ 80% interest in Oncor, the largest electricity transmission and distribution system in Texas, for approximately $9.5 billion. The Agreement obligated Debtors to pay NextEra $275 million if NextEra did not ultimately acquire Debtors’ interest in Oncor and Debtors either sold to someone else or otherwise emerged from bankruptcy, with several exceptions. If the Public Utility Commission of Texas (PUCT) did not approve the merger, payment would not be triggered if the Agreement was “terminated . . . by [NextEra] . . . and the receipt of PUCT Approval (without the imposition of a Burdensome Condition) [wa]s the only condition . . . not satisfied or waived in accordance with this Agreement.” About a year after approving the Agreement, and after PUCT expressed concern about the condition, the bankruptcy court granted a motion for reconsideration and disallowed the Termination Fee in the event that the PUCT declines to approve the transaction and, as a result, the agreement is terminated, regardless of whether the Debtors or NextEra subsequently terminates the agreement. Were it not for that order, NextEra would be entitled to the $275 million. The Third Circuit affirmed, rejecting NextEra’s arguments that the motion was untimely and, alternatively, that the motion should have been denied on the merits because the termination fee provision, as originally drafted, was an allowable administrative expense under 11 U.S.C. 503(b). View "In re: Energy Future Holdings" on Justia Law

by
Petitioners sought to prevent the expansion of Transco’s interstate natural gas pipeline facilities, arguing that the Federal Energy Regulatory Commission (FERC) violated the Natural Gas Act (NGA), 15 U.S.C. 717–717z and environmental protection statutes, by arbitrarily approving Transco’s proposed project. Petitioners also argued that the New Jersey Department of Environmental Protection (NJDEP) violated state law by improperly issuing permits required under federal law before commencement of construction activities and by denying the petitioners’ request for an adjudicatory hearing to challenge the permits, based only on the NJDEP’s allegedly incorrect belief that the New Jersey regulations establishing the availability of such hearings were preempted by federal law. The Third Circuit concluded that the challenges to FERC’s orders lacked merit because no discharge-creating activity can commence without New Jersey independently awarding Transco with a Section 401 permit; no activities that may result in a discharge can follow as a logical result of just FERC’s issuance of the certificate. FERC adequately addressed the need for the project and its cumulative impacts, as required by the National Environmental Policy Act. The court remanded to NJDEP. NJDEP misunderstood the scope of the NGA’s assignment of jurisdiction to the federal Courts of Appeals, rendering unreasonable the sole basis for its denial of the petitioners’ request for a hearing--preemption. View "Township of Bordentown v. Federal Energy Regulatory Commission" on Justia Law