Justia U.S. 3rd Circuit Court of Appeals Opinion Summaries
Articles Posted in Energy, Oil & Gas Law
In re: MTE Holdings LLC
Chenault-Vaughan Family Partnership ("Chenault"), a royalty interest holder in a Texas mineral estate, sued Centennial Resources Operating, LLC ("Centennial"), the site operator, for wrongly withholding royalties. The Bankruptcy Court awarded summary judgment to Centennial. Chenault appealed to the District Court, where the parties consented to proceed before a Magistrate Judge. The Magistrate Judge affirmed the Bankruptcy Court’s judgment, and Chenault appealed to the United States Court of Appeals for the Third Circuit.The Third Circuit first addressed whether the Magistrate Judge had jurisdiction to enter final judgment in the bankruptcy appeal. The court concluded that, with the consent of the parties and a referral by the district court, a magistrate judge may enter final judgment in a bankruptcy appeal. This conclusion was supported by the broad consent authority granted to magistrate judges under 28 U.S.C. § 636(c), the repeal of the statutory provision that previously prohibited such referrals, and the supervisory authority retained by Article III judges.On the merits, the Third Circuit reviewed the Bankruptcy Court’s summary judgment on two claims: trespass to try title and royalties under the Texas Natural Resources Code ("TNRC"). The court affirmed the summary judgment for Centennial on the trespass-to-try-title claim, finding that Centennial did not unlawfully enter the land and dispossess Chenault, as Luxe, a cotenant, had the right to extract minerals and permit Centennial to operate.However, the court vacated the summary judgment on the TNRC claim. The court found that there were genuine disputes of material fact regarding whether Centennial was obligated to pay Unit B royalties to Chenault, particularly concerning the Division Order and Centennial’s knowledge of MDC’s non-signature on the Unit B JOA. The case was remanded to the Magistrate Judge with instructions to remand to the Bankruptcy Court for further proceedings on the TNRC claim. View "In re: MTE Holdings LLC" on Justia Law
Transcontinental Gas Pipe Line Co LLC v. Pennsylvania Environmental Hearing Board
The case involves Transcontinental Gas Pipe Line Company, LLC (Transco), a natural gas company that sought to abandon and expand its pipeline facilities in Pennsylvania and New Jersey. To do so, Transco needed a Certificate of Public Convenience and Necessity from the Federal Energy Regulatory Commission (FERC), which it obtained. However, the certificate was subject to conditions, including that Transco receive three additional permits from the Pennsylvania Department of Environmental Protection (PADEP). After receiving these permits, Transco began its pipeline project. However, three environmental advocates filed an administrative appeal with the Environmental Hearing Board (EHB) challenging PADEP's issuance of the permits. In response, Transco initiated a lawsuit in the District Court seeking to enjoin the administrative appeal, arguing that the Natural Gas Act preempts the state law allowing the appeal.The District Court rejected Transco's preemption arguments and denied its motion for a preliminary injunction. Transco appealed this decision to the United States Court of Appeals for the Third Circuit. The Court of Appeals affirmed the District Court's decision, finding that none of the theories of preemption advanced by Transco or the state agency applied in this case. The Court held that the Natural Gas Act does not expressly preempt administrative appeals to the EHB, nor does it field preempt such appeals. The Court also found that the possibility of multiple challenges in different fora to PADEP permitting decisions under the Clean Water Act for interstate natural gas pipelines does not impose an obstacle to the purposes of the Natural Gas Act. Therefore, the Court concluded that Transco's motion for a preliminary injunction was correctly denied. View "Transcontinental Gas Pipe Line Co LLC v. Pennsylvania Environmental Hearing Board" on Justia Law
Constellation Energy Generation LLC v. FERC
In this case, a group of electricity providers challenged orders by the Federal Energy Regulatory Commission (FERC), arguing that FERC allowed a new auction rule to apply retroactively to a pending auction. The auction was overseen by PJM Interconnection L.L.C., a FERC-regulated wholesale market operator. PJM had halted the auction upon realizing that the results could lead to a high clearing price for a particular region due to a faulty assumption regarding the participation of certain resources. PJM sought and received permission from FERC to amend the tariff to allow it to adjust the Locational Deliverability Area (LDA) Reliability Requirement downward, reflecting the lack of participation of certain resources.The petitioners argued that this violated the filed rate doctrine, which prohibits retroactive rates. The court agreed, finding that the tariff amendment was retroactive because it altered the legal consequence attached to a past action: it allowed for the use of a different LDA Reliability Requirement than the one PJM had calculated and posted. The court noted that equitable considerations did not factor into the application of the filed rate doctrine, emphasizing the importance of predictability in the electricity markets.The court granted the petitions and vacated the orders in relevant part, specifically the portion of FERC’s orders that permitted PJM to apply the tariff amendment to the 2024/25 capacity auction.
View "Constellation Energy Generation LLC v. FERC" on Justia Law
Posted in:
Energy, Oil & Gas Law, Government & Administrative Law
Electric Power Supply Association v. FERC
Several power providers and their associations challenged orders from the Federal Energy Regulatory Commission (FERC) that retroactively permitted a new auction rule to apply to a pending auction. The rule was implemented by PJM Interconnection L.L.C., the entity responsible for the auction, to determine the auction's results. The petitioners claimed FERC's orders violated the filed rate doctrine, which prohibits retroactive rates. The case background involves the Federal Power Act (FPA), which grants FERC exclusive jurisdiction over rates for the transmission and wholesale of electric energy in interstate commerce. The FPA requires all related rates, rules, and regulations to be "just and reasonable" and not unduly preferential.The petitioners and FERC agreed that the filed rate was the PJM Open Access Transmission Tariff, which sets the procedures governing PJM’s capacity auctions. PJM administered a capacity auction in December 2022 for capacity in the June 2024 – May 2025 period. A dispute arose when PJM sought to adjust the Locational Deliverability Area (LDA) Reliability Requirement due to perceived anomalies in the auction results, which would have resulted in a high clearing price for a certain region. FERC approved the proposed adjustment, which was challenged by the petitioners.The court agreed with the petitioners and held that the orders of FERC were retroactive and thus violated the filed rate doctrine. The court granted the petitions and vacated the orders in the relevant part. The court emphasized that the equities play no role in the application of the filed rate doctrine and that predictability is of paramount importance in electricity markets. It concluded that FERC’s disregard of the filed rate doctrine creates unpredictability in the markets and may ultimately harm consumers who buy electricity in those markets. View "Electric Power Supply Association v. FERC" on Justia Law
Posted in:
Energy, Oil & Gas Law, Government & Administrative Law
NRG Power Marketing v. FERC
A group of power providers contested orders from the Federal Energy Regulatory Commission (FERC) that permitted a new auction rule to retroactively apply to a pending auction. The petitioners argued that this violated the filed rate doctrine, which forbids retroactive rates. The auction, administered by the PJM Interconnection LLC (PJM), aimed to ensure reliable electric supply at competitive prices. PJM halted the auction, seeking FERC's permission to amend certain auction parameters it had already posted, which, if left uncorrected, might have led to a high clearing price for a specific region. FERC approved the amendment and allowed it to apply to the halted auction, which the petitioners challenged. The United States Court of Appeals for the Third Circuit agreed with the petitioners, stating that the amendment was retroactive as it altered the legal consequence attached to PJM's past action in the auction. The court granted the petitions and vacated the portion of FERC's orders that allowed the amendment to apply to the auction in question. View "NRG Power Marketing v. FERC" on Justia Law
Constellation Energy Generation LLC v. FERC
The case involves a dispute over the Federal Energy Regulatory Commission (FERC) allowing a new auction rule to apply retroactively to a pending auction. This auction was administered by PJM Interconnection L.L.C., an entity responsible for running the auction. The petitioners, electric suppliers and their trade associations, contended that FERC's orders violated the filed rate doctrine, which forbids retroactive rates.The United States Court of Appeals for the Third Circuit found that the Tariff Amendment was retroactive because it altered the legal consequence attached to a past action when it allowed PJM to use a different Locational Deliverability Area (LDA) Reliability Requirement than the one it had calculated and posted. The court noted that the Tariff Amendment, therefore, violated the filed rate doctrine.The court ruled that the doctrine's predictability is crucial because electricity markets depend on it. FERC’s disregard of the filed rate doctrine created unpredictability in the markets, potentially eroding confidence in the markets and ultimately harming consumers who buy electricity in those markets.The court granted the petitions for review and vacated the portion of FERC’s orders that allowed PJM to apply the Tariff Amendment to the 2024/25 capacity auction. View "Constellation Energy Generation LLC v. FERC" on Justia Law
Electric Power Supply Association v. FERC
This case involved several petitioners challenging orders of the Federal Energy Regulatory Commission (FERC), which allowed a new auction rule to retroactively apply to an auction that was already underway. The auction was managed by PJM Interconnection L.L.C. (PJM), which ran the auction based on a tariff (filed rate) that set out specific procedures. The petitioners argued that FERC's orders violated the filed rate doctrine, which prohibits retroactive rates.The United States Court of Appeals for the Third Circuit agreed with the petitioners. The court found that the new rule was retroactive because it altered the legal consequences attached to past actions. Specifically, the rule allowed PJM to use a different Locational Deliverability Area (LDA) Reliability Requirement than the one it had calculated and posted.The court noted that, while FERC's orders were seemingly intended to prevent potential economic harm to consumers, the filed rate doctrine's emphasis on predictability and the necessity of adherence to approved rates were paramount. The court concluded that FERC's orders, by allowing a change to the rules of an auction already in progress, introduced unpredictability into the electricity market, potentially eroding market confidence.Therefore, the court granted the petitions for review and vacated the portion of FERC's orders that allowed PJM to apply the new rule to the auction that was already underway. The court did not strike down the rule entirely, leaving open the possibility of it being applied to future auctions. View "Electric Power Supply Association v. FERC" on Justia Law
Posted in:
Energy, Oil & Gas Law, Government & Administrative Law
NRG Business Marketing LLC v. FERC
In this case, a group of electricity suppliers and their trade associations challenged orders of the Federal Energy Regulatory Commission (FERC) that permitted PJM Interconnection L.L.C., a wholesale market operator, to apply a new auction rule retroactively to a pending auction. The petitioners argued that FERC's orders violated the filed rate doctrine, which prohibits retroactive rates. The United States Court of Appeals for the Third Circuit agreed and granted the petitions, vacating the relevant parts of the orders.The central issue revolved around the Locational Deliverability Area (LDA) Reliability Requirement, a key parameter in PJM's auction process. Prior to the auction, PJM had miscalculated the LDA Reliability Requirement, which led to a potential price increase for a specific region. To correct this, PJM sought FERC's permission to amend the tariff to allow for a downward adjustment of the LDA Reliability Requirement. FERC granted this permission, allowing the new rule to apply to the ongoing auction, which the petitioners argued was a retroactive change in violation of the filed rate doctrine.The court found that the tariff amendment was indeed retroactive as it altered the legal consequence attached to a past action, specifically, PJM's calculation and posting of the LDA Reliability Requirement. The court held that the filed rate doctrine did not yield to equities and that the tariff amendment's retroactivity created instability in the electricity market. Consequently, the court vacated the portion of FERC's orders that allowed PJM to apply the tariff amendment to the 2024/25 capacity auction.
View "NRG Business Marketing LLC v. FERC" on Justia Law
PJM Power Providers Group v. FERC
In a case involving the Federal Energy Regulatory Commission (FERC) and a group of petitioners, the petitioners challenged FERC's decision to allow a new auction rule to be applied retroactively. The auction in question, run by PJM Interconnection LLC, determines the selling price for electricity. The petitioners argued that the retroactive application of the new rule violated the filed rate doctrine, which prohibits retroactive rates.The court agreed with the petitioners, granting their petitions and vacating the orders in question. The court found that the new rule was retroactive because it changed the legal consequence of a past action, specifically the calculation and posting of the Locational Deliverability Area (LDA) Reliability Requirement. The LDA Reliability Requirement is a parameter used in the auction to determine the amount of electricity that must be produced to meet peak demand.The court noted that while the new rule allowed PJM to adjust the LDA Reliability Requirement downward to account for certain resources' lack of participation in the auction, the original tariff did not provide for this adjustment. Therefore, the new rule altered the legal consequence of the past action of calculating and posting the LDA Reliability Requirement.The court concluded that the retroactive application of the new rule violated the filed rate doctrine, and therefore FERC's approval of the rule was not in accordance with the law. The court emphasized that the doctrine's goal of predictability is of utmost importance and that FERC and the courts must respect the doctrine to ensure stability in the markets. As a result, only the portion of FERC's orders that allowed the new rule to be applied to the specific 2024/25 capacity auction was vacated.
View "PJM Power Providers Group v. FERC" on Justia Law
Posted in:
Energy, Oil & Gas Law, Government & Administrative Law
PJM Power Providers Group v. Federal Energy Regulatory Commission
In this case, a group of energy providers and their trade associations challenged orders by the Federal Energy Regulatory Commission (FERC), which permitted a new auction rule to be applied retroactively to a pending auction. The auction was run by PJM Interconnection L.L.C., an entity that administers capacity auctions to ensure a reliable electric supply at competitive prices. PJM had applied the new rule to determine the auction results, but the petitioners argued that FERC's orders violated the filed rate doctrine, which forbids retroactive rates.The Third Circuit Court of Appeals sided with the petitioners. It found that the new auction rule, which allowed for an adjustment to the Locational Deliverability Area (LDA) Reliability Requirement (a key parameter in the auction process) after it had been calculated and posted, was retroactive. This was because it altered the legal consequence attached to a past action, in violation of the filed rate doctrine. The court ruled that FERC's orders were arbitrary and capricious and not in accordance with the law, and therefore vacated the portion of FERC's orders that allowed PJM to apply the new rule to the 2024/25 capacity auction. View "PJM Power Providers Group v. Federal Energy Regulatory Commission" on Justia Law
Posted in:
Energy, Oil & Gas Law, Government & Administrative Law